200 MW
AGE Combined Cycle Power Plant
Engineering, procurement and construction management (EPCM) of all project phases
Completed
Group reference · Combined cycle power plant
Completed62 MWLüleburgaz, Kırklareli, Türkiye
A 62 MW natural gas-fired combined cycle plant in Lüleburgaz, in the Thrace region of Türkiye, connected to the national grid at 154 kV. Enprode Engineering managed it from engineering to commissioning, including the HV switchyard and the overhead transmission line.
References of Enprode Engineering & Construction, the Enprode group’s engineering company, as the group publishes them.
Enprode Engineering was awarded the Delta combined cycle power plant project in September 2007. Delta Energy A.Ş., an independent power producer and a subsidiary of the Palmet Group, is the investor.
An aeroderivative gas turbine generator is the prime mover. A heat recovery steam generator uses its exhaust heat to raise steam for a steam turbine generator, and an air-cooled condenser condenses the exhaust steam. Natural gas is the single fuel, for base load.
Both generators deliver 11.5 kV at 50 Hz. Each is connected to the national grid at 154 kV through its own step-up power transformer in the air-insulated switchyard.
The simple cycle went into operation in April 2009, and the plant entered commercial operation on the basis of the ministry’s acceptance dated 18 September 2009.
| Gross power output | 62 MWe |
|---|---|
| Gross electrical efficiency | 53% |
| NOx emissions | 50 mg/Nm³ |
| Fuel | Natural gas |
| Gas turbine | 1 × GE LM6000 Sprint, aeroderivative |
| Gas turbine site rating | 46,949 kWe |
| Exhaust gas flow | 474.8 t/h |
| Exhaust gas temperature | 452 °C |
| Heat recovery steam generator | Vertical, drum type |
| Steam turbine | Dresser-Rand, frame RD9MOP |
| Steam turbine output | 14 MWe |
| HP steam | 58 bar / 439 °C |
| LP steam | 4 bar / 227 °C |
| Generator voltage | 11.5 kV, 50 Hz |
| Grid connection | 154 kV, air-insulated switchyard |
200 MW
Engineering, procurement and construction management (EPCM) of all project phases
Completed
870 MW
Balance-of-plant (BOP) engineering, procurement, installation, commissioning and start-up services
Completed
775 MW
Engineering, procurement, erection, commissioning and start-up of balance-of-plant (BOP) systems
Completed